Fri, 20th November 2009
Jim Ennis Construction Ltd V Combined Stabilisation Ltd
The sub-sub-contractor remained bound by the final account agreement despite the sub-contractor having wrongly withheld the sum of the sum of £7,362 from the payment of £142,901 towards the agreed final account sum of £707,500 in breach of that agreement