Aveat Heating Ltd v Jerram Falkus Construction Ltd
The non-compliance of one of the adjudication provisions in clause 38A.5 in the GC/Works Sub-Contract with section 108(2)(c) had the effect under section 108(5) that the Scheme for Construction Contracts replaced the adjudication procedure in the GC/Works Sub-Contract in its entirety