Quantity Surveying - Case Study 4
 
Sun, 1st December 2002
 
 

Quantity Surveying - Case Study 4

 

Leisure & Arts - Sport Erewash

 

Brief:

 

Erewash borough council appointed TVP as Employers Agent, CDM Co-ordinator, Project Manager and Clerk of Works for the re-design and refurbishment of an existing sports facility over two phases.

 

The development consisted of: a six lane sports track, with all-weather pitch and floodlighting; a refurbished cricket pavilion with associated facilities and parking; plus a new tennis building with 4nr tennis courts and associated facilities.
 

 

Location:

Ilkeston, Derbyshire
 

Value:

£ 6,300,000

  
The Pinnacle at Night
External View
The Pinnacle at Night
Track View
 
 
category Case Studies